In plain terms

Two UK industry planning documents, from 2022 and 2025, each state a beam-intensity design figure in the 230-245 watts-per-square-metre range, but neither traces that number back to any official safety or interference standard: the 2022 report gives no source for its figure, and the 2025 report, for a system planned to launch in 2033, cites only an earlier internal Frazer-Nash report.

The claim as recorded

A 2022 Frazer-Nash/ESA cost-benefit report states a beam-centre design intensity of 245 W/m2 "at the centre of the rectenna," and a 2025 UK feasibility report (RAF036, Frazer-Nash/Space Solar/Imperial) separately assumes 230 W/m2 as a "power intensity limit" for a planned 2033-launch system, citing only an earlier Frazer-Nash internal report for that figure; neither document cites ICNIRP, IEEE C95.1, Ofcom, or any published exposure or interference standard for either number.

Scope and limits

Shows an absence of a standards citation, a directly confirmed finding from reading the text, not an inference about why the figure is uncited; does not establish that the figure is wrong, only that its provenance is not documented in these two current planning documents.

What it assumes

The absence is read from the full text of both documents. The 2022 report gives no source for the 245 W/m2 sentence (SRC-078 PDF p.19 and p.20), and none of its 82 pages contains ICNIRP, IEEE, C95 or Ofcom. In the 2025 report, IEEE appears only in journal citations (PDF p.14 and p.92) and Ofcom only in a footnote on frequency choices (PDF p.15, footnote 11), not for the 230 W/m2 figure.

Where it comes from

SRC-078 Study on Cost-Benefit Analysis of Space-Based Solar Power Generation for Terrestrial Energy...
SRC-076 RAF036/2425: Feasibility of Small-Scale Space Based Solar Power Systems for Early Market...
SRC-078 Study on Cost-Benefit Analysis of Space-Based Solar Power Generation for Terrestrial Energy...
SRC-076 RAF036/2425: Feasibility of Small-Scale Space Based Solar Power Systems for Early Market...
Frazer-Nash/ESA (2022), SRC-078 PDF p.19 and p.20 (the passage is printed twice; the p.20 footer reads "Page 20 of 82" and the p.19 footer misprints it as "Page 45 of 82", as do the footers of PDF p.6 to p.18): "The peak intensity of the microwave beam at the centre of the rectenna on the ground is 245 W/m2."; no source is given for that sentence. RAF036 (2025), SRC-076 PDF p.29, footnote 31: "An intensity limit of 230 W/m2 is assumed in line with Frazer-Nash's SBSP Engineering Feasibility Report".

Basis: power density, W/m2, at beam/rectenna centre; no averaging basis stated

Related records
Answers question
QST-001 not published in this release

Cite this

energyaperture.com/c/clm-0152

CLM-0152, Energy Aperture, as of 2022; 2025.

Connected records

Other published records linked to this one. A list, not a judgement.

Also from SRC-076
CLM-0018The most recent UK government report calls 230 watts per square metre a limit to be reached because it lowers cost, and cites an earlier...
CLM-0019The report sets out Space Solar's plan: a small in-orbit test, then 31 megawatts in 2030, 150 megawatts in 2033, and 650 megawatts in...
CLM-0213The study assumes that connecting a ground receiving site to the electricity grid costs about GBP 150,000 for every megawatt of power the...
CLM-0214Six different solar-power-satellite designs each claim that turning the electricity collected on the ground into grid-ready power is 90 to...
CLM-0215Any UK ground receiving station that wants to connect to the electricity grid must be able to supply or absorb a type of power called...
CLM-0216The UK's fast-response grid support services need a generator to react within seconds, at any moment over a 4-hour period. A ground...
CLM-0503Under the international radio rules as revised at the 2023 world radio conference, there is no radio-frequency allocation for beaming power...
CLM-0517Every date in the plan -- the ground demo (2026), the demo mission (2027-28), 2030, 2033 and 2036 -- is a hope, not a booking, and the...
More on the source page.
Also from SRC-078
CLM-0189A separate 2022 study for the European Space Agency, by Frazer-Nash and London Economics, estimates the cost of electricity from a first...
CLM-0190This European study finds that a full Europe-wide space solar power programme would cost about 418 billion euros in today's money but...
CLM-0191This 2022 report is one of two parallel studies the European Space Agency commissioned on the costs and benefits of space solar power: this...
CLM-0280A 2022 ESA-commissioned study modelled that the first European space solar power satellite could produce electricity at a cost of 106 to...
CLM-0281The study tested how much the cost of launching material into space changes the price of space solar power. It used launch-cost data from...
CLM-0282A 2022 ESA-commissioned study modelled that, from 2022 to 2070, space solar power for Europe could deliver a net economic benefit of about...
CLM-0539A UK consultancy, working for the European Space Agency and using the same design as its reference point, actually published a full weight...
CLM-0967The 2022 European study assumed it takes two years to build a satellite in orbit, and that getting parts launched could be the thing that...
More on the source page.