CALC-054
Bottom-up lifecycle cost and discounted-cash-flow LCOE, both designs
What this is
This is the project's own arithmetic, published in full so it can be checked rather than taken on trust. It is not a source. Every input it uses is cited to a record, and the conclusion it reaches only carries as far as those inputs do.
Feeds CLM-0240, CLM-0241, CLM-0246. SHARED - three claims, one section. Answers QST-004.
Script. lcoe-model.py SECTION 4 build_lifecycle() (line 282), SECTION 5
build_annual_timeline() (line 416) and lcoe_dcf() (line 448), reported by SECTION 6
section_baseline() (line 572).
Why it was needed. This is the validation step everything else in the model rests on. If the bottom-up totals did not match NASA's published totals, no divergence found downstream could be attributed to method rather than to a broken build.
Inputs. All of CALC-053's, plus:
| Quantity | Value | Source | Stated or assumed |
|---|---|---|---|
| Discount rate | 3 per cent | SRC-012 p.56, a Government-financing assumption | STATED |
| CapEx spread | evenly over a 7.375-yr build, zero energy output during build | - | ASSUMED - this model's own timeline, not sourced |
| Ground-segment cost | a one-off lump at commissioning | - | ASSUMED |
| Maintain-phase costs | two equal lumps at operational years 10 and 20 | - | ASSUMED |
| Operate- and Dispose-phase costs | taken as fixed lumps from SRC-012 | SRC-012 | STATED, 12-15 per cent of lifecycle total, not independently re-derived |
| RD2 capacity factor and build duration | 0.60 and 12.625 yr | SRC-012 | STATED, taken directly, not varied |
Working, transcribed as the comparison table the script prints.
this model NASA published ratio
RD1 CapEx $91.2 B $90.6 B 1.01 x
RD1 FOM $186 B $186 B 1.00 x
RD1 launches 2,321 2,321 exact
RD1 DCF LCOE 0.6231 $/kWh 0.61 $/kWh 1.02 x
RD2 CapEx $138 B $137 B 1.01 x
RD2 FOM $298 B $297 B 1.00 x
RD2 launches 3,973 3,960 1.00 x
RD2 DCF LCOE 1.0153 $/kWh 1.59 $/kWh 0.64 xResult. RD1 agrees to 2 per cent. RD2 does not, and the disagreement is the informative half. The underlying cost build matches within 1 per cent for both designs, so the RD2 gap cannot come from mass, launches or manufacturing. That isolates capacity factor and build duration as the place to look, which is what CALC-055 does.
Conclusion, and it is a method point. Close agreement on RD1 combined with a specific, explained divergence on RD2 is worth more than agreement on both would have been. A correct cost total does not guarantee a correct $/kWh conversion, and this pair of results is what demonstrates that.
Where this fails. An order-of-magnitude check. It does not confirm NASA OTPS's underlying spreadsheet, which was not available. The annual cash-flow timeline is this model's own construction and is not sourced - three of the four assumptions in the inputs table above are this model's, and they are the ones a challenger should attack first.
Cite this
energyaperture.com/calc/calc-054
CALC-054. The working above, not a source document.