In plain terms

The UK government's own cost model expects deep geothermal power, which it treats as an early-stage technology, to become much cheaper by 2050 than a first-of-a-kind plant would be in 2030.

The claim as recorded

UK DESNZ's Electricity Generation Costs 2025 Annex A projects deep granite geothermal levelised cost falling from GBP 270/MWh (2030, first-of-a-kind) to GBP 52/MWh (2050), as first-of-a-kind cost is shed with deployment.

Scope and limits

This is a projection for an immature technology, not a track record; deep geothermal has not been deployed at the scale DESNZ's 2050 figure assumes. GBP basis, not converted to USD here, because an FX conversion must not be made silently. These are not power-only costs: the report (p.23) says deep geothermal "was modelled as a combined heat and power (CHP) system to allow heat revenues to be accounted for within the LCOE", assuming 20% of heat sold, and each year's build-up carries a negative "Additional Costs" line (-70 in 2030, -71 in 2050). The estimates cover granite only.

What it assumes

DESNZ's own modelled first-of-a-kind-to-mature cost reduction trajectory for a technology not yet deployed at scale in the UK.

Where it comes from

SRC-155 Electricity Generation Costs 2025, Annex A: additional estimates and key assumptions., 2026
SRC-154 Electricity Generation Costs 2025, published January 2026, updated March 2026., 2026
Annex A, sheet "Additional Estimates 2030", column "Deep Granite Geothermal (FOAK)", row "Total": 270 GBP/MWh; sheet "Additional Estimates 2050", column "Deep Granite Geothermal", row "Total": 52 GBP/MWh. Both sheets state "All costs in 2024 real GBP prices". The report (p.11) lists deep geothermal for power among technologies "assumed to currently reflect more nascent (FOAK) technologies" and states that "For less established technologies there will generally be some learning associated with increased deployment that is factored into future cost estimates."

Basis: GBP2024, real

Related records
Answers question
QST-021 not published in this release

Cite this

energyaperture.com/c/clm-0544

CLM-0544, Energy Aperture, as of 2025.

Connected records

Other published records linked to this one. A list, not a judgement.

Also from SRC-154
CLM-0270DESNZ estimated in its 2025 report that a new large solar farm built in the UK and commissioned in 2030 would generate power at about 60...
CLM-0271DESNZ estimated that a new gas power station in the UK, run almost continuously, would generate power at about 111-112 pounds per...
CLM-0272The UK government's 2025 cost report does not give a single number for what it would cost to make solar or wind power available around the...
CLM-0524Every UK-specific or typical-country cost-of-capital figure found sits well below the 20% rate Frazer-Nash used, even at the top of DESNZ's...
Also from SRC-155
CLM-0270DESNZ estimated in its 2025 report that a new large solar farm built in the UK and commissioned in 2030 would generate power at about 60...
CLM-0271DESNZ estimated that a new gas power station in the UK, run almost continuously, would generate power at about 111-112 pounds per...